2013-10-02Not ApplicableLeakage of Contaminated Water from the Top Plate of a Tank at B Area (South)JapanFUKUSHIMA-DAIICHI
2015-09-15Not ApplicableLeakages of water from the dikes in tank areas storing contaminated waterJapanFUKUSHIMA-DAIICHI
2015-05-29Not ApplicableContaminated water being transferred to turbine building of unit 3 from 1000 tons notch tank was leaking from the cracked pressure hoseJapanFUKUSHIMA-DAIICHI
2016-04-20Not ApplicableLeakage from Piping Transferring RO-Concentrated Water to G-6 Tank AreaJapanFUKUSHIMA-DAIICHI
2011-04-12INES 7Re-evaluation of INES rating; Effect to the Nuclear Facilities from the earthquake on east area of JapanJapanFukushima Daiichi
2013-08-19INES 3Contaminated water leakage from a water tankJapanFUKUSHIMA DAIICHI
1992-10-18INES 0UNSCHEDULED SHUTDOWN DUE TO STEAM LEAKAGE FROM AN OUTLET PIPE OF A HIGH PRESSURE TURBINEJapanFUGEN ATR
2014-05-17INES 1Exposure of a temporary worker in excess of annual dose constraint during transfer operation of irradiated neutron detector.IndiaTARAPUR-4
1991-04-07INES 1MISGRAPPLING OF FUEL BUNDLE MB-140 IN THE CORE OF UNIT NO. 2IndiaTARAPUR-2
1991-04-25INES 0FINGERS INJURY WHILE WORKING ON PRIMARY STEAM ISOLATION VALVEIndiaTARAPUR-2
1992-02-12INES 0UNIT-2 REACTOR SCRAM DUE TO GRID DISTURBANCESIndiaTARAPUR-2
1992-03-31INES 0REACTOR UNIT NO.2 SCRAM ON TOTAL LOSS OF POWERIndiaTARAPUR-2
1992-04-19INES 0REACTOR UNIT NO.2 SCRAM ON CONSENSER LOW VACUUMIndiaTARAPUR-2
1992-05-13INES 1UNIT-2 EMERGENCY CONDENSER LOOP A TUBE FAILUREIndiaTARAPUR-2
1992-08-19INES 1STARTUP AUXILIARY TRANSFORMER X03B OUTAGE EXCEEDING SEVEN DAYS LIMITIndiaTARAPUR-2
1992-07-31INES 0UNIT NO. 2 REACTOR SCRAM ON PRM HIGH FLUXIndiaTARAPUR-2
1990-11-19INES 0REACTOR SCRAM ON PRM HIGH FLUX SUBSEQUENT TO SPURIOUS ACTUATION OF REACTOR RELIEF VALVES A & B (SRUOR-1-90-8)IndiaTARAPUR-1
1990-11-24INES 0REACTOR SCRAM ON TOTAL LOSS OF OFF-SITE AC POWER (CLASS IV). SRUOR-1-90-9.IndiaTARAPUR-1
1991-02-22INES 0LOWERING OF REACTOR WATER LEVEL BELOW CORE SPRAY ACTUATION LEVELIndiaTARAPUR-1
1991-03-16INES 0REACTOR SCRAM ON TOTAL LOSS OF OFF-SITE POWERIndiaTARAPUR-1
1991-07-10INES 0UNIT NO. 1 REACTOR SCRAM ON PRM HIGH FLUXIndiaTARAPUR-1
1991-07-16INES 0UNIT NO. 1 REACTOR SCRAM ON PRM HIGH FLUXIndiaTARAPUR-1
1992-06-19INES 0UNIT NO. 1 SCRAM ON PRM CH. 6 & IRM CH. 9 KICKING UP DURING FUNCTIONAL CHECKSIndiaTARAPUR-1
1992-06-15INES 0REACTOR UNIT NO. 1 SCRAM ON TOTAL LOSS OF POWERIndiaTARAPUR-1
1992-08-21INES 1SOIL CONTAMINATION WHILE PUMPING OUT RAIN WATER FROM TAPS-TRAP TRANSFER LINE INSPECTION PITIndiaTARAPUR-1