01-11-1996 | INES 2 | One of the emergency core cooling systems - the core spray system - was unavailable at Oskarshamn-2 | OSKARSHAMN-2, Sweden |
11-11-1996 | INES 0 | Small leak in one steam generator | KOZLODUY-6, Bulgaria |
18-07-1996 | INES 1 | Erroneous line-up before start-up of vent pipe valves to the scrubber system | FORSMARK-1, Sweden |
08-11-1995 | INES 2 | Degradation of the control rod system due to sticking of one control rod assembly | PAKS-2, Hungary |
14-08-1996 | INES 0 | Reactor trip caused by blown fuses | KRSKO, Slovenia |
13-08-1996 | INES 1 | Water leak into a hot cell at the Studsvik research establishment | Studsvik Nuclear AB, Sweden |
03-08-1996 | [N/A] | Rupture of a freon storage tank | CERNAVODA-1, Romania |
24-07-1996 | INES 1 | On-site radioactive contamination | KHMELNITSKI-1, Ukraine |
12-07-1996 | INES 1 | Degradation of essential service water (ES'W) for a year due to a defficient design modification | ASCO-1, Spain |
06-04-1996 | INES 2 | Sticking of a control rod cluster during reactor scram | BELLEVILLE-1, France |
13-05-1996 | INES 2 | Degradation of seismic stops of the reactor pit | CHINON-B1, France |
16-05-1996 | INES 1 | Disturbance of forced reactor coolant circulation in cold shutdown condition | KOZLODUY-5, Bulgaria |
28-06-1996 | INES 0 | Radioactive contamination in the reactor hall | CHERNOBYL-1, Ukraine |
12-06-1996 | INES 1 | Degraded pressure subpression (PS) function | BARSEBECK-2, Sweden |
21-05-1996 | [N/A] | Injuries in the NPP Dukovany non-related to nuclear and radiation safety | DUKOVANY-1, Czech Republic |
15-05-1996 | INES 1 | Small leak of radioactive water from auxiliary building no. 2 | KOZLODUY-3, Bulgaria |
30-04-1996 | INES 1 | Exceeding allowed maximum primary coolant temperature during planned outage | KHMELNITSKI-1, Ukraine |
24-04-1996 | INES 1 | Radioactive contamination at the Unit N3 | CHERNOBYL-3, Ukraine |
15-04-1996 | INES 1 | Penetration of primary coolant and low level contamination of hermetic box | BOHUNICE-4, Slovakia |
24-03-1995 | INES 2 | CONFIRMED DOSE ABOVE STATUTORY DOSE LIMIT PROBABLY DUE TO A WOUND | BNFL, Sellafield, United Kingdom |
04-03-1996 | INES 1 | FAILURE OF A CONTAINMENT ISOLATION VALVE AT A PERIODICAL TEST | OSKARSHAMN-1, Sweden |
27-11-1995 | INES 3 | RADIOACTIVE CONTAMINATION IN THE REACTOR BUILDING | CHERNOBYL-1, Ukraine |
21-01-1996 | INES 1 | A PART OF THE RESIDUAL HEAT REMOVAL SYSTEM - THE AUXILIARY CONDENSER - TEMPORARILY NOT AVAILABLE | OSKARSHAMN-1, Sweden |
09-02-1996 | INES 0 | REACTOR SHUTDOWN BY THE FAST-ACTING SCRAM SYSTEM DUE TO SPURIOUS SIGNALS OF INCREASED PRESSURE IN THE ISOLATION CONTROL VALVES ROOM | IGNALINA-1, Lithuania |
31-01-1996 | INES 1 | Reactor scram followed by the actuation of safety valve in the reactor primary circuit | NIIAR Inst., Dimitrovgrad, Russian Federation |
15-11-1995 | INES 1 | DEVIATION FROM TECHNICAL SPECIFICATIONS | RINGHALS-4, Sweden |
13-12-1995 | INES 0 | SMALL RADIOACTIVITY RELEASE | KRSKO, Slovenia |
26-08-1995 | INES 1 | DESIGN DEFICIENCIES IN DIESEL GENERATORS FOUND DURING EXTENDED TESTING | OSKARSHAMN-1, Sweden |
01-01-1995 | INES 1 | DESIGN DEFICIENCIES IDENTIFIED IN SEPARATION OF ELECTRICAL SYSTEM, AVOIDANCE OF COMMON CAUSE FAILURES IN THE REACTOR PROTECTION SYSTEM AND OVERPRESSURE RELEASE IN THE AUX BUILD. | OSKARSHAMN-1, Sweden |
01-01-1995 | INES 0 | CRACKS IN THE REACTOR CORE SHROUD IN THE LID OF THE SHROUD AND IN REACTOR VESSEL INTERNALS | OSKARSHAMN-1, Sweden |