Uit de publicatie:

CHAPTER 1

INTRODUCTION

The nuclear industry and the Nuclear Regulatory Commission (NRC) have 
complementary responsibilities in assuring the safe operation of commercial 
nuclear powerplants. NRC establishes rules, regulations, standards, and guides for 
the construction and operation of nuclear powerplants. The nuclear industry has 
the direct responsibility to design, construct, test, and operate the plants according
to these rules. NRC, through its licensing and inspection programs attempts to 
assure that the industry is fulfilling this responsibility, and that public health and 
safety is protected.

The current NRC inspection program has evolved over the past 22 years as the 
nuclear industry and the safety awareness of the public have grown. Since the first 
commercial nuclear powerplant became operational at Shippingport, Pennsylvania, 
in 1957, 70 nuclear powerplants have been constructed and licensed to operate 
throughout the United States. Ninety-eight more nuclear reactors are in various 
stages of construction. Inspections at these plants are made by so-called "regional 
inspectors" from five NRC regional offices.

On the basis of NRC statistics, about 25 percent of the regional inspector's time is 
spent onsite, inspecting the reactor owner's activities. Most of the balance of the 
time is spent in the regional offices preparing for inspections, evaluating inspection 
findings, and documenting inspections. Consequently, the regional inspection 
program places considerable confidence in the capability of the reactor owner and 
the accuracy and completeness of his statements and documents.

In June 1974, NRC's Office of Inspection and Enforcement began a 2-year trial 
program of assigning inspectors to locations at or near nuclear power reactor sites. 
The program involved assigning two NRC inspectors to locations from which they 
could inspect a total of four reactor sites. In evaluating the trial program, the 
Office of Inspection and Enforcement concluded that placing inspectors at reactor 
sites (resident inspectors) was viable, specifically because it made more efficient
and effective use of inspectors' time.