The North West Nuclear Energy Plants and Pioneers 

Risley 1946
In 1946 Mr. Christopher Hinton Hater Lord Hinton of Bankside) was chosen to 
direct a new Atomic Energy Production Division of the Ministry of Supply. His 
instructions were to build factories to carry out four main processes - to extract 
uranium metal or uranium hexafluoride from ore concentrates; to irradiate the metal 
in nuclear piles; to extract plutonium from the irradiated metal and refine it; and to 
separate Uranium 235 by diffusion.

Springfields 1946
A paramount consideration of the new Production Division was to get uranium 
production going as quickly as possible and the Risley engineers decided that much 
time would be saved if the plant could be built in one of the factories put up during 
the war to manufacture munitions. An examination of the factories available led to 
the choice of Springfields as being the one which best met the requirements.

Windscale 1947
For the operation of plutonium-producing piles and for chemical reprocessing of the 
irradiated fuel to separate the plutonium from the depleted uranium and the fission 
products a new atomic energy site was established at Windscale.

Capenhurst 1949
A new atomic energy site at Capenhurst, Cheshire, for the production, by gaseous 
diffusion, of uranium enriched in the naturally occurring fissile isotope uranium 235 
was announced in 1949.

Calder Hall 1953
Construction work began in 1953 on the world's first industrial-scale nuclear power 
station at Calder Hall, Cumbria, adjacent to the Windscale site. The original plans 
were for two reactors with a turbine hall between and two large cooling towers at 
one end, this now being known as the Calder 'A' station.

Windscale Advanced Gas-Cooled Reactor (AGR) 1957
The Atomic Energy Authority started work on the AGR system in 1957 within a year 
of raising power on the first Calder Hall reactor. Construction of the experimental 
AGR on the Windscale site started in November 1958, and criticality was achieved 
in August 1962.

Heysham Nuclear Power Station 1983
Arising from the developments by the UKAEA, the CEGB (NW Region) own and 
operate four nuclear power stations. Two Magnox stations are located at Wylfa and 
Trawsfynydd in North Wales. At 840 MW output, Wylfa is the largest and the last 
of the Magnox stations.