date | INES | title | location |
05-10-2012 | INES 2 | Overexposure of a worker | IRM group sa - Alleur, Belgium |
25-08-2008 | INES 3 | Iodine-131 release in the environment | IRE-Fleurus, Belgium |
24-07-2006 | INES 2 | Lost of type A radioactive package during transport from Brussels to Bucharest | International Transport, Romania |
10-01-2022 | INES 2 | Higher dose rate in an operating area due to inappropriate positioning of a Co-60 source | Institute of Isotopes Ltd. Budapest, Hungary |
20-02-2012 | [n/a] | Spillage from water pipe in the room with nuclear materials | Institute for Nuclear Sciences Vinca, Serbia |
24-10-2016 | INES 1 | Fuel fail and emission from research reactor | Institute for Energy Technology, Halden, Norway |
08-09-2014 | INES 2 | Overexposure of radiographyworker over the annual limit | Inspecta, Randaberg, Stavanger, Norway |
16-09-2010 | INES 2 | Radiography overexposure | Inspecta Oy/Kotka, Finland |
05-07-1993 | INES 0 | FIRE AT COOLING TOWERS | INR-PITESTI, Romania |
26-05-2010 | INES 2 | Contamination of 6 workers during the recovery of a gammagraphy Co-60 source | industrial radiography, France |
04-05-1991 | INES 3 | PERSONNEL OVEREXPOSURE DURING PRECOMMISSIONING OPERATIONS INVOLVING HOT CELL | IGNALINA-2, Lithuania |
15-10-1992 | INES 0 | LEAKAGE FROM REACTOR CIRCUIT PIPE, DIAMETER 26 | IGNALINA-2, Lithuania |
15-10-1992 | INES 1 | LEAKAGE OF REACTOR CIRCUIT PIPE 76 MM DIAMETER FROM REACTOR CHANNEL 32-24 TO THE DRUM SEPARATOR | IGNALINA-2, Lithuania |
27-01-1994 | INES 0 | MANUAL REACTOR SHUTDOWN CAUSED BY THE FAILURE OF THE MANUAL REACTOR CONTROL ROD SYSTEM | IGNALINA-2, Lithuania |
24-02-1994 | INES 1 | DETERIORATION OF THE PRIMARY CIRCUIT INTEGRITY | IGNALINA-2, Lithuania |
08-07-1994 | INES 0 | AUTOMATIC REACTOR SHUTDOWN CAUSED BY SPURIOUS CLOSING OF THE GATE VALVE AT THE PIPELINE FEEDING THE MAIN CONDENSATE HEATER WITH HEATING STEAM | IGNALINA-2, Lithuania |
11-07-1994 | INES 1 | MALFUNCTION IN THE SYSTEM OF NEUTRON CONTROL OF REACTOR POWER FOLLOWING THE REPLACEMENT OF A CONTROL ROD SWITCH | IGNALINA-2, Lithuania |
22-11-1995 | INES 1 | AUTOMATIC REACTOR UNLOADING DUE TO SPURIOUS OPENINGS OF VALVES BETWEEN A GROUP OF ECCS PRESSURIZED TANKS AND REACTOR | IGNALINA-2, Lithuania |
30-11-1995 | INES 1 | OVEREXPOSURE OF OPERATOR DURING CALIBRATION OF IN-CORE SENSORS | IGNALINA-2, Lithuania |
07-01-1996 | INES 0 | MANUAL REACTOR SHUTDOWN DUE TO LEAKAGE IN BLEED WATER RETURN PIPELINE | IGNALINA-2, Lithuania |
18-09-1990 | INES 2 | SPURIOUS ACTUATION OF 2 MAIN SAFETY VALVES OUT OF TWELVE | IGNALINA-1, Lithuania |
04-10-1990 | INES 2 | TG 2 TRIP DUE TO DEENERGIZATION OF 6 & 0.4 KV BUSES AND FAILURE OF TG STANDBY OIL PUMP TO START | IGNALINA-1, Lithuania |
04-11-1992 | INES 0 | DENT ON THE PIPE OF REACTOR CHANNEL 10-33 TO THE DRUM SEPARATOR | IGNALINA-1, Lithuania |
18-01-1994 | INES 0 | REACTOR SHUTDOWN CAUSED BY THE LEAKAGE DETECTED IN ONE OF THE REACTOR BUILDING ROOMS | IGNALINA-1, Lithuania |
07-02-1994 | INES 1 | FAILURE OF THE FOAM FIRE-EXTINGUISHING SPRINKLER SYSTEM TO OPERATE FOR 16 HOURS DUE TO FROZEN PIPES | IGNALINA-1, Lithuania |
21-08-1994 | INES 0 | REACTOR SHUTDOWN CAUSED BY LEAKAGE THROUGH A JOINT WELD IN THE ECCS PIPEWORK | IGNALINA-1, Lithuania |
09-08-1994 | INES 0 | AUTOMATIC REACTOR SHUTDOWN CAUSED BY GENERATOR TRIP | IGNALINA-1, Lithuania |
03-11-1994 | INES 0 | INFRINGEMENT OF THE REACTOR PRIMARY CIRCUIT INTEGRITY | IGNALINA-1, Lithuania |
12-11-1995 | INES 0 | AUTOMATIC REACTOR UNLOADING DUE TO TURBOGENERATOR TRIP BY OPERATOR | IGNALINA-1, Lithuania |
09-02-1996 | INES 0 | REACTOR SHUTDOWN BY THE FAST-ACTING SCRAM SYSTEM DUE TO SPURIOUS SIGNALS OF INCREASED PRESSURE IN THE ISOLATION CONTROL VALVES ROOM | IGNALINA-1, Lithuania |