The real cost of nuclear electricity in the UK
J. W. Jeffery

PAST AND PRESENT COSTS: cost comparison in real terms

The article 'The real costs of nuclear power in the UK', (1) discussed the effects of 
inflation on capital costs and gave the details and results of approximate calculations 
of electricity costs from nuclear and coal-fired stations if inflation corrections were 
applied. (2) These calculations were based on the figures of comparative generation 
costs in p/kWh given for the first time in the Statistical Yearbook of the Central 
Electricity Generating Board (CEGB) for 1978/9. As that article went to press, the 
1979/80 Annual Report (AR) and Statistical Yearbook (SY) were issued, and in a 
'Note added in proof it was 'hoped to publish a full analysis of Appendix 3 in due 
course'. (3)
Comparative generation costs of some nuclear and coal-fired stations were listed in 
Tables 1-3 of App 3 (of 1979/80, CEGB, AR) and the detailed capital costs of these 
are now public property as the result of a parliamentary question (given under 
'historic costs' in Tables 1, 3 and 5). No oil-fired stations are included because 
'oil is no longer an option' ( 1979/80, CEGB, AR, App 3, Note 14).
The method of calculation is exemplified in Table 3, dealing with the comparison of 
just two stations, Hinkley Point B and Drax A (Table 2 of 1979/80 CEGB, AR, A pp 
3). Table 4 gives the results after correction for inflation and compares these with
the CEGB historic costs.
The same methods have been applied to the stations of Table 1 (text and 1979/80 
CEGB, AR, App 3) but only the results are given in Table 2. (4) Table 5 gives the 
data and calculations for stations under construction (Table 3, 1979/80 CEGB, AR, 
App 3) and Table 6 the results. These illustrate the peculiar effects which can come 
about from mixing historic costs and high interest rates, with fixed future costs 
and a 5% interest rate.
During the preparation of this manuscript the 1980/81 Annual Report of the CEGB 
was published In a number of ways this does not follow on from the 1979/80 Annual 
Report. Current cost accounting (CCA) is employed for the first time and the 
Appendix corresponding to Appendix 3 of 1979/80 has changed, notably in giving 
a 40 year lifetime to coal-fired stations and in discontinuing the net effective 
cost (NEC) calculations. The 1979/80 Annual Report was intimately linked with the 
House of Commons Select Committee on Energy and the Monopolies and Mergers
Commission inquiries, and all three used 1979/80 or March 1980 prices.