Laka Foundation

Publication Laka-library:
Transmission from Torness (1981)

AuthorSSEB
DateFebruary 1981
Classification2.05.8.50/02 (UNITED KINGDOM - TORNESS)
Front

From the publication:

SOUTH OF SCOTLAND ELECTRICITY BOARD

TRANSMISSION FROM TORNESS

This leaflet outlines the main factors which influenced the Board's proposals for 
connections from Torness to the transmission system. It also gives some other 
background information on transmission of electricity.

INTRODUCTION

Nuclear power stations are needed to supplement coal for producing electricity to 
meet consumers' demands. 
SSEB derive present supplies of nuclear based energy from their nuclear stations at 
Hunterston in Ayrshire and from the British Nuclear Fuels Limited's station at 
Chapelcross in Dumfriesshire. The magnox stations at Hunterston and Chapelcross 
have been in operation since the early 1960s. Both represent significant steps on the 
road to the peaceful use of atomic energy and both have helped to make it possible 
for Scottish consumers to obtain their electricity at a lower average price per unit 
than is paid by consumers elsewhere in the United Kingdom. The Board's second 
nuclear power station, Hunterston 'B', first supplied power to the grid in 1976 and 
has greatly boosted supplies of nuclear energy to Scottish consumers.
Torness will be the Board's third nuclear power station and its two 660 megawatt 
reactor units are scheduled to be operational in 1987 and 1988. From Torness a new 
supply of nuclear based electricity will be available close to the load centres in the 
east of the Board's network.