date | INES | title | location  |
18-05-1993 | INES 2 | SEEPAGE FROM A WASTE DRUM | BNFL, Sellafield, United Kingdom |
18-10-1993 | INES 0 | ACID SPILLAGE IN THORP | BNFL, Sellafield, United Kingdom |
04-07-1995 | INES 2 | SKIN EXPOSURE IN EXCESS OF DOSE LIMIT | BNFL, Sellafield, United Kingdom |
24-03-1995 | INES 2 | CONFIRMED DOSE ABOVE STATUTORY DOSE LIMIT PROBABLY DUE TO A WOUND | BNFL, Sellafield, United Kingdom |
03-02-1997 | INES 2 | Spillage of active liquor | BNFL, Sellafield, United Kingdom |
02-02-1997 | INES 2 | Release of airborne activity into the workplace resulted in a building evacuation | BNFL, Sellafield, United Kingdom |
11-04-1999 | INES 2 | Spillage of radioactive materials | BNFL, Sellafield, United Kingdom |
18-10-1999 | INES 2 | Incorrectly packaged radioactive sources | BNFL, Sellafield, United Kingdom |
20-04-2005 | INES 3 | Fractured Pipe in Thorp Reprocessing plant | BNFL, Sellafield, United Kingdom |
25-08-2016 | INES 1 | Loss of a device containing radioactive sources | Boguszow-Gorce, Poland, Poland |
20-09-1991 | INES 1 | INCREASE ACTIVITY OF WASTE WATER FROM THE A-1 AND V-1 NPPS | BOHUNICE-1, Slovakia |
12-05-1991 | INES 3 | RELEASE OF ACTIVE LIQUID FROM STORAGE TANK | BOHUNICE-1, Slovakia |
15-01-1991 | INES 2 | FIRE OF BUSES OF SECOND CATEGORY OF RELIABILITY BUSES | BOHUNICE-2, Slovakia |
21-12-1993 | INES 1 | TURBINE TRIP DUE TO PRESSURE DROP IN STEAM GENERATOR MAIN COLLECTOR | BOHUNICE-2, Slovakia |
09-12-1993 | INES 1 | EXCEEDING OF CL-CONCENTRATION IN PRIMARY CIRCUIT WATER | BOHUNICE-2, Slovakia |
22-04-1993 | INES 1 | INTERVENTION OF AUTOMATIC POWER CONTROL (APC) DUE TO SPURIOUS SIGNAL | BOHUNICE-2, Slovakia |
23-02-1993 | INES 1 | FALL DOWN OF CONNECTOR FRAGMENTS INTO THE REACTOR VESSEL | BOHUNICE-2, Slovakia |
27-04-1995 | INES 0 | REACTOR SCRAM DUE TO A REACTOR PROTECTION SPURIOUS SIGNAL | BOHUNICE-2, Slovakia |
18-10-1993 | INES 1 | VIOLATION OF CHEMICAL REGIME OF STEAM GENERATOR FEED WATER (SGFW) | BOHUNICE-3, Slovakia |
03-06-1993 | INES 1 | DIESEL GENERATOR START FAILURE | BOHUNICE-3, Slovakia |
20-06-1995 | INES 0 | REACTOR SCRAM DURING INSPECTION OF GROUND CONNECTION | BOHUNICE-4, Slovakia |
15-04-1996 | INES 1 | Penetration of primary coolant and low level contamination of hermetic box | BOHUNICE-4, Slovakia |
15-06-2000 | INES 1 | Unplanned exposure of workers | BOHUNICE-4, Slovakia |
02-12-2010 | INES 2 | Several mine workers overexposed by X-rays | Boliden Mineral, Gällivare, Sweden |
30-06-2015 | INES 2 | Bordeaux University: discovery of radioactive sources and incidental exposure of persons | Bordeaux University, France |
02-08-2013 | INES 2 | Uncontrolled release of radioactive effluents into the public sewerage system | Bordeaux university hospital, France |
14-10-2014 | INES 2 | A practitioner’s regulatory annual exposure dose limit was exceeded | Bordeaux University Hospital - Pellegrin Hospital, France |
24-03-2022 | INES 2 | Exposure of radiographer over annual statutory dose limit | BorsodChem Co. Ltd, Hungary |
23-05-2021 | INES 1 | Failure of a defectoscope during industrial radiography test | Borsodchem PLC, Hungary |
21-11-1996 | INES 2 | Operation of unit with insufficient containment function | BORSSELE, Netherlands |