date | INES | title | location  |
04-10-2011 | INES 2 | Contamination of workers during inspection | Belgoprocess, Belgium |
12-03-2001 | INES 2 | Risk of recirculation system valves becoming jammed in 5 NPPs | BELLEVILLE-1, France |
06-04-1996 | INES 2 | Sticking of a control rod cluster during reactor scram | BELLEVILLE-1, France |
20-06-2017 | INES 2 | Emergency diesel generators auxiliary systems not compliant with seismic requirements on the 1300 MW reactors (8 sites - 20 reactors) | BELLEVILLE-1, France |
02-08-2017 | INES 2 | Risk of loss of heat sink in case of an earthquake - 20 reactors concerned | BELLEVILLE-1, France |
22-06-1991 | INES 2 | DEFECTIVE WELDS IN LOW PRESSURE SAFETY INJECTION SYSTEM | BELLEVILLE-2, France |
24-05-1991 | INES 2 | UNAVAILABILITY OF REACTOR LEVEL MEASUREMENT | BELLEVILLE-2, France |
10-07-1991 | INES 2 | INADVERTENT DILUTION OF THE PRIMARY FLUID DURING A COLD SHUTDOWN | BELLEVILLE-2, France |
11-06-1998 | INES 2 | Automatic shutdown of the reactor caused by spurious triggering of the containment spray system and jamming of a control cluster in the high position during this shutdown | BELLEVILLE-2, France |
23-12-1992 | INES 2 | RADIOACTIVITY RELEASE OUTSIDE LIQUID RADWASTE STORAGE BOUNDARY | BELOYARSKY-3(BN-600), Russian Federation |
07-10-1993 | INES 1 | RADIOACTIVE CONTAMINATION OF THE UNIT ROOMS DUE TO REACTOR COOLANT LEAK IN THE AUXILIARY SYSTEM | BELOYARSKY-3(BN-600), Russian Federation |
09-09-2000 | INES 0 | Beloyarsk NPP Unit 3 scram due to events in the operation of the Urals power system | BELOYARSKY-3(BN-600), Russian Federation |
20-08-1974 | INES 2 | EXCESSIVE DEPRESSURIZATION OF THE PRIMARY CIRCUIT DUE TO A PRESSURIZER SAFETY VALVE THAT FAILED TO CLOSE | BEZNAU-1, Switzerland |
11-09-1991 | INES 0 | FAILURE OF TWO PRESSURIZER SPRAY LINES | BEZNAU-1, Switzerland |
10-04-1992 | INES 0 | LOSS OF AC POWER DURING REFUELING WITH UNLOADED REACTOR | BEZNAU-2, Switzerland |
03-08-2009 | INES 2 | Exposure of two workers in excess of statutory annual dose limits | BEZNAU-2, Switzerland |
22-11-2013 | INES 1 | Two radioactive sources containing Co-60 lost or stolen | Bełchatów Power Station (coal-fired power plant), Poland |
23-02-1995 | INES 0 | SMALL LEAKAGE OF PRIMARY COOLANT AT NPP BIBLIS, UNIT B | BIBLIS-B, Germany |
10-07-1991 | INES 3 | RADIOACTIVE WATER SPILLAGE ON THE PLANT TERRITORY WHILE TRANSPORTING CASK WITH FUEL FRAGMENTS TO THE DRY RADWASTE REPOSITORY | BILIBINO GEN, Russian Federation |
14-03-1998 | INES 2 | Radiation overexposure of personnel while performing refuellig activities | BILIBINO UNIT D, Russian Federation |
09-10-2001 | INES 1 | Iridium source lost in a stolen van | BINCH, Belgium |
28-12-1999 | INES 2 | Partial loss of safeguards systems as a result of external flooding | BLAYAIS-1, France |
24-04-2013 | INES 2 | Accidental exposure of a worker exceeding annual regulatory limit to the skin | BLAYAIS-4, France |
18-08-2015 | INES 2 | Irradiation of a worker during scheduled NNP outage at Le Blayais | BLAYAIS-4, France |
01-05-1995 | INES 2 | ELEVATED URANIUM LUNG BURDEN | BNFL SPRINGFIELDS, United Kingdom |
09-06-1997 | INES 0 | Fire involving used extract ventilation filters | BNFL SPRINGFIELDS, United Kingdom |
08-09-1992 | INES 3 | PLUTONIUM NITRATE LEAK IN CELL | BNFL, Sellafield, United Kingdom |
12-01-1993 | INES 2 | SIGNIFICANT SPILLAGE OF PLUTONIUM LADEN SOLVENT | BNFL, Sellafield, United Kingdom |
12-02-1993 | INES 1 | PLUTONIUM RECOVERY PLANT, B204 | BNFL, Sellafield, United Kingdom |
12-02-1993 | INES 2 | OVEREREXPOSURE OF A RADIOGRAPHY INSPECTOR AS A RESULT OF A WOUND | BNFL, Sellafield, United Kingdom |